GCF Renewal Works in Brittany

Work underway from Auray to the Quiberon Peninsula
In Brittany, in the coastal department of Morbihan, work has begun on the most demanding of the railway renewal sites currently being carried out by GCF in France. As lead company of the consortium with CLMTP and Groupe Pigeon, GCF France has deployed its French subsidiaries ETMF, Prestafer and Delcourt Rail on the project.
The “AUQUI Project” concerns the renewal of line 473 000, which runs from Auray, a town of 12,000 inhabitants overlooking the Atlantic Gulf of Morbihan, to the small town of Quiberon, located at the southern end of the peninsula of the same name.
The railway line was inaugurated in 1882. Single-track, non-electrified and equipped with simplified signalling, it has a maximum operating speed of 60 km/h. Its 26 km length, with gradients of up to 15%, includes 31 level crossings, 6 passenger stops and two stations with escape routes. Today, it is served by 10 trains a day, which connect Auray and Quiberon in approximately 43 minutes.
Following the initial phase of preparatory surveys and topographical measurements, the main phase of the project involves the complete renewal of the track, including the installation of new sleepers and rails, the assembly of track panels, stress-free temperature adjustment and bringing the track into compliance. The final phase will include track-bed cleaning, various finishing works and checks on level, squareness and sleeper spacing.
The works are carried out on weekdays, either during the day or at night, depending on the various phases and work activities. Around sixty workers are involved. Three service yards for machinery storage and material stockpiling have been set up in Ploemel, near level crossing 452, and at Saint-Pierre-de-Quiberon railway station.
“In compliance with French regulations,” explains Sabino Carbone, from GCF’s French management, “strict safety measures have been adopted in accordance with the S9A1 provisions, which protect personnel working on or near railway lines open to traffic, and the S9A3 provisions, which govern access to lines closed to traffic. In practice, every worker must constantly carry a safety certificate and an access authorisation issued by the Activity Manager, who has received specific training to ensure safety.”
Further GCF worksites in France
The line 110 000 Molsheim–Saales worksite was completed in mid-July, with 4,186 metres renewed using the P95 train and 2,042 metres rehabilitated using the C75-2C, while the remaining sections were renewed and rehabilitated using conventional equipment under the Hors Suite operating regime. GCF France is currently working in several regions across France.
In Grand Est, where work was completed a few days ago on the Novéant–Frouard line for the replacement of approximately 8 km of rails, the workers have been deployed slightly further south, in the Haute-Marne department, to launch a new worksite based primarily in Merrey, which will replace the rails along line 032 000 Chalindrey–Bourmont.
In the Auvergne-Rhône-Alpes region, the SAO Modernisation Paris–Clermont worksite will continue until mid-November and will involve modifications to the railway alignment and associated works, including level surveys over 10 km of line, stress-free temperature adjustment and work on the electrical tension line.
In the Centre–Val de Loire region, with a worksite set up at the Avord service yard, GCF is working along the Bourges–Saincaize line to replace rails over 16 km of track and to carry out complete track and ballast renewal (RVB) on additional sections at 8 level crossings. The works, which began in August, will continue until April 2027.
Finally, urgent tamping and levelling works began last week on line 905 000, known as the “Alps line”. GCF, acting as deputy lead contractor for Maiarail, is working there with a Matisa B50 tamping machine and a team of workers.
The single-track, non-electrified line runs along the Alpine border between France and Switzerland, with numerous tunnel sections and steep gradients. The simultaneous execution of other urgent line works, the difficulty of accessing the work areas due to heavy traffic along the RD1075 road and, last but not least, the presence of steep rock faces from which falling stones and rock debris could be triggered, also as a result of machinery vibrations, are critical factors at this cross-border worksite, which is being managed with the utmost attention to safety requirements.

News GCF 2026
- Milan-Limbiate: the “Frecciarancio” tramway gets a new lease of life
- GCF Renewal Works in Brittany
- GCF in Berlin with the best of the railway industry
- Padua SIR2: Precision and Innovation for Lot 2
- Ponte al Pino: 550-ton bridge launched
- From Construction Sites to Research: GCF at the Forefront of Railway Innovation
- T2 Bergamo–Villa d'Almè: Towards Completion
- GCF Research to Be Presented at the 9WCSCM
- GCF France at work in Molsheim
- Val Venosta Railway enters the electric era
- GCF Group company expands into Germany
- Renewal and Rehabilitation Worksites with GCF
- Canada: Track Maintenance Awarded to a GCF Group Company
- RFI Approval for GCF’s PAI-PL System
- AV/AC Brescia - Verona: finish line in sight
- STOP: enhanced safety on GCF and GEFER worksites
- New GCF Worksite in Luxembourg
- Val Pusteria, renewed railway inaugurated
- GCF worksites active in France
- Toulouse Metro Line B: GCF at Work
- Master’s Degree for Railway Engineers: Applications Now Open
News GCF 2025
- GCF confirmed among the “Excellences”
- GCF Solutions at Saudi Rail 2025
- GCF, a Champion of Sustainability
- New railway site in Besançon for GCF France
- Railway Safety looks to “Futuro”
- In the Grand Est of France with GCF
- GCF at work for the Toulouse Metro Line B
- HS/HC Brescia - Verona: GCF at work
- In Münster with GCF for the 29th IAF
- GCF - Transalp, Work in Progress
- GCF at High Speed Towards Marrakech
- Tunnel Rail Route 10: from Design to Construction
- Successful Verification for GCF’s PAI-PL
- GCF France. Starting from Paris